1. |
Consider the implicit details between, before and after successive steps in/within the order while doing time computations on a CPM network. (FP => Forward Pass; BP => Backward Pass; LET => Late Event Time; EET => Early Event Time; TF => Total Float; PD => Project Duration; AD => Activity Duration)The correct sequence of computation would be |
A. | EET, PD, LET, TF |
B. | EET, PD, LET, AD |
C. | AD, EET, BP, PD |
D. | FP, EET, TF, PD |
Answer» D. FP, EET, TF, PD | |