Consider the implicit details between, before and after successive steps in/within the order while doing time computations on a CPM network. (FP => Forward Pass; BP => Backward Pass; LET => Late Event Time; EET => Early Event Time; TF => Total Float; PD => Project Duration; AD => Activity Duration)The correct sequence of computation would be

A. EET, PD, LET, TF
B. EET, PD, LET, AD
C. AD, EET, BP, PD
D. FP, EET, TF, PD
Answer» D. FP, EET, TF, PD