Consider the given project network, where numbers along various activities represent the normal time. The free float on activity 4 – 6 and the project duration, respectively, are |
| A. | 2, 13 |
| B. | 0, 13 |
| C. | -2, 13 |
| D. | 2, 12 |
| Answer» B. 0, 13 | |