Consider the following statements regarding contact stabilization process:1. Primary settling tank is not required in some cases.2. BOD removal occurs in two stages.3. Aeration volume requirements are approximately 50% of those of a conventional – or tapered – aeration plant.4. Returned sludge is aerated for 30 min to 90 min in sludge aeration tank.Which of the above statements are correct? |
A. | 1, 2, 3 and 4 |
B. | 1 and 4 only |
C. | 1, 2 and 3 only |
D. | 2, 3 and 4 only |
Answer» D. 2, 3 and 4 only | |