Consider the following statements :A critical activity in a CPM network has1. The longest duration of all activities2. zero total float3. zero for float4. The shortest duration of all activitieswhich one of the statements given above are correct ? |
| A. | 1 and 2 |
| B. | 1 and 3 |
| C. | 2 and 3 |
| D. | 3 and 4 |
| Answer» B. 1 and 3 | |