Consider the following statements:1. In work breakdown structure, top-down approach is adopted.2. Duration along critical path is the shortest duration permissible.3. PERT is probabilistic in its approach.Which of the above statements are correct? |
| A. | 1 and 2 only |
| B. | 1 and 3 only |
| C. | 2 and 3 only |
| D. | 1, 2 and 3 |
| Answer» E. | |