1.

Consider the following statements:1. In work breakdown structure, top-down approach is adopted.2. Duration along critical path is the shortest duration permissible.3. PERT is probabilistic in its approach.Which of the above statements are correct?

A. 1 and 2 only
B. 1 and 3 only
C. 2 and 3 only
D. 1, 2 and 3
Answer» E.


Discussion

No Comment Found