Consider the AoA network of a project shown in the given figure. (Activities are designated by alphabets and durations are shown around the stem of the arrow.) The critical path will be

A. 1-2-3-6-7-8
B. 1-2-3-5-7-8
C. 1-2-4-5-7-8
D. 1-2-4-6-7-8
Answer» C. 1-2-4-5-7-8