Consider the AoA network of a project shown in the given figure. (Activities are designated by alphabets and durations are shown around the stem of the arrow.) The critical path will be |
A. | 1-2-3-6-7-8 |
B. | 1-2-3-5-7-8 |
C. | 1-2-4-5-7-8 |
D. | 1-2-4-6-7-8 |
Answer» C. 1-2-4-5-7-8 | |