1.

Clay layer A with single drainage and coefficient of consolidation Cv takes 6 months to achieve 50% consolidation. The time taken by clay layer B of the same thickness with double drainage and coefficient of consolidation Cv/2 to achieve the same degree of consolidation is

A. months
B. months
C. 2 months
D. 4 months
Answer» B. months