

MCQOPTIONS
Saved Bookmarks
1. |
Calculate number of Kanbans if the hourly demand is 200 units, lead time is 12 hours, container capacity is 144 units, and variation in lead time is 15%. |
A. | 23 |
B. | 22 |
C. | 21 |
D. | 20 |
Answer» E. | |