An engineer supervising a concreting work observes major defect in some portion after opening formwork. What step is required to be performed first? |
| A. | Impose penalty to the contractor |
| B. | Change the contractor’s manpower |
| C. | Consult the designer to investigate the consequences and perform corrective measures |
| D. | Recommend patch up work to hide the defected portion. |
| Answer» D. Recommend patch up work to hide the defected portion. | |