1.

An engineer supervising a concreting work observes major defect in some portion after opening formwork. What step is required to be performed first?

A. Impose penalty to the contractor
B. Change the contractor’s manpower
C. Consult the designer to investigate the consequences and perform corrective measures
D. Recommend patch up work to hide the defected portion.
Answer» D. Recommend patch up work to hide the defected portion.


Discussion