A type of estimate required if there is change amounting to more than 5% of the original value due to price hiking or change in specification, but does not include any major change in structural design is called |
| A. | Detailed estimate |
| B. | Revised estimate |
| C. | Supplementary estimate |
| D. | Rough cost estimate |
| Answer» C. Supplementary estimate | |