A spillway of an irrigation project is to be studied by means of a model constructed to a scale of 1 : 9. The prototype discharge is 1000 m3/s. Neglecting the viscous and surface tension effects, the required flow rate for the model is |
| A. | 12.35 m3/s |
| B. | 111.11 m3/s |
| C. | 4.11 m3/s |
| D. | 1.37 m3/s |
| Answer» D. 1.37 m3/s | |