A saturated clay layer with single drainage face takes 4 years to attain 50% degree of consolidation. If the clay layer had double drainage, then the time required to attain 50% degree of consolidation is |
A. | 8 years |
B. | 4 years |
C. | 2 years |
D. | 1 year |
Answer» E. | |