| 1. |
A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is |
| A. | 3 |
| B. | 9 |
| C. | 81 |
| D. | 27 |
| Answer» C. 81 | |