A PERT activity has an optimistic time of 3 days, pessimistic time of 15 days and an expected time of 7 days. The most likely time of the activity is |
| A. | 5 days |
| B. | 6 days |
| C. | 7 days |
| D. | 9 days |
| Answer» C. 7 days | |