A job-design to be time-studied has fatigue and delay allowance of 10 minutes & 25 minutes per 8-hour shift. In addition 25 minutes personal time is permitted in a shift. Then, the total allowance factor necessary to calculate Standard Time for this activity will be _____. |
| A. | 1.143 |
| B. | 0.8 |
| C. | 12 |
| D. | None of these |
| Answer» B. 0.8 | |