A job-design to be time-studied has fatigue and delay allowance of 10 minutes & 25 minutes per 8-hour shift. In addition 25 minutes personal time is permitted in a shift. Then, the total allowance factor necessary to calculate Standard Time for this activity will be _____.

A. 1.143
B. 0.8
C. 12
D. None of these
Answer» B. 0.8