A fill having a volume of 150, 000 cm is to be constructed at a void ratio of 0.8. The borrow pit soil has a void ratio of 1.4. The volume of soil required (in cubic metres) to be excavated from the borrow pit will be

A. 1, 87, 500
B. 2, 00, 000
C. 2, 10, 000
D. 2, 50, 000
Answer» C. 2, 10, 000