

MCQOPTIONS
Saved Bookmarks
1. |
A fill having a volume of 150, 000 cm is to be constructed at a void ratio of 0.8. The borrow pit soil has a void ratio of 1.4. The volume of soil required (in cubic metres) to be excavated from the borrow pit will be |
A. | 1, 87, 500 |
B. | 2, 00, 000 |
C. | 2, 10, 000 |
D. | 2, 50, 000 |
Answer» C. 2, 10, 000 | |