1.

Which of the following is not an advantage of implementing TPM?

A. Improved equipment reliability
B. Reduced equipment downtime
C. Increased equipment downtime
D. Lower maintenance and production costs
Answer» D. Lower maintenance and production costs
2.

TPM ensures an improved return on investment.

A. True
B. False
Answer» B. False
3.

Improved safety is one of the benefits of implementing TPM.

A. True
B. False
Answer» B. False
4.

If the overall equipment effectiveness is 40%, availability 82%, quality score 96%, calculate the performance efficiency?

A. 50.8%
B. 60.8%
C. 70.8%
D. 40.8%
Answer» B. 60.8%
5.

If the theoretical cycle time per unit is 0.5 minutes/unit, the number of units is 400, and the operating time is 400 minutes, calculate performance efficiency.

A. 20%
B. 30%
C. 40%
D. 50%
Answer» E.
6.

If the loading time is 400 minutes and downtime is 60 minutes, calculate availability.

A. 81%
B. 83%
C. 85%
D. 87%
Answer» D. 87%
7.

A machine that was supposed to run for 10 hours suffers a breakdown and runs only for 9 hours. Calculate availability.

A. 89%
B. 90%
C. 91%
D. 92%
Answer» C. 91%
8.

What is the quality score if an asset produces 15000 units out of which 500 are defective?

A. 92.67%
B. 94.67%
C. 96.67%
D. 98.67%
Answer» D. 98.67%
9.

If availability is 85%, performance efficiency is 50%, and the rate of quality products is 98%, then find out the overall equipment effectiveness?

A. 42%
B. 50%
C. 32%
D. 60%
Answer» B. 50%