| 1. |
The measure not advisable to prevent landslide is __________ |
| A. | Soil nailing |
| B. | Geo synthetic fibre |
| C. | Soil stabilization by any method |
| D. | Retaining wall |
| Answer» D. Retaining wall | |
| 2. |
The failure due to shear occurs in __________ |
| A. | Slides |
| B. | Falls |
| C. | Flows |
| D. | Complex slides |
| Answer» B. Falls | |
| 3. |
The landslide doesn t take place due to __________ |
| A. | Sliding |
| B. | Falling |
| C. | Flowing |
| D. | Breaking |
| Answer» E. | |
| 4. |
The landslide denotes __________ |
| A. | Downward and upward movement of hill slope material |
| B. | Disintegration of rocks |
| C. | Earthquake on hill |
| D. | Breaking of rock |
| Answer» B. Disintegration of rocks | |
| 5. |
The frequent problem on the hill road is __________ |
| A. | Earthquake |
| B. | Landslide |
| C. | Soil erosion |
| D. | Seepage |
| Answer» C. Soil erosion | |
| 6. |
The important structure constructed above the road with out impacting the load is called __________ |
| A. | Gallery |
| B. | Drainage |
| C. | Camber |
| D. | Crown |
| Answer» B. Drainage | |
| 7. |
The problems in snowfall region, of snow is not cleared is overcome by __________ |
| A. | Hill markers |
| B. | Snow markers |
| C. | Traffic signal |
| D. | Closing the road |
| Answer» C. Traffic signal | |
| 8. |
The preventive measure adopted in hill road don t include __________ |
| A. | Stabilization of soil |
| B. | Grass turf |
| C. | Stone masonry |
| D. | Brick masonry |
| Answer» E. | |
| 9. |
Catch water drains, sloping drain, road side drains, catch pit and culverts are periodically cleared to prevent __________ |
| A. | Landslide |
| B. | Over flow of water |
| C. | Earthquake |
| D. | Snowfall |
| Answer» C. Earthquake | |