| 1. | The rollers that uses both tamping and kneading is __________ | 
| A. | Plain roller | 
| B. | Vibratory roller | 
| C. | Sheep foot roller | 
| D. | Pneumatic roller | 
| Answer» D. Pneumatic roller | |
| 2. | The plasticity index for a sub grade should be less than __________ | 
| A. | 45 | 
| B. | 35 | 
| C. | 25 | 
| D. | 15 | 
| Answer» D. 15 | |
| 3. | The free swelling index of soil should be less than __________ | 
| A. | 50 | 
| B. | 60 | 
| C. | 70 | 
| D. | 80 | 
| Answer» B. 60 | |
| 4. | The liquid limit of soil for embankment construction is __________ | 
| A. | Less than 70% | 
| B. | Less than 90% | 
| C. | Less than 60% | 
| D. | Less than 45% | 
| Answer» B. Less than 90% | |
| 5. | What is the minimum spacing between the two sand beds? | 
| A. | 1.0 m | 
| B. | 1.5 m | 
| C. | 2.0 m | 
| D. | 2.5 m | 
| Answer» E. | |
| 6. | The consolidation can be achieved faster by __________ | 
| A. | Clay | 
| B. | Peat | 
| C. | Sand drains | 
| D. | Sand filter | 
| Answer» D. Sand filter | |
| 7. | The investigation of embankment should be carried out for __________ | 
| A. | Twice the height of embankment | 
| B. | Thrice the height of embankment | 
| C. | Exact height of embankment | 
| D. | Half height of embankment | 
| Answer» B. Thrice the height of embankment | |
| 8. | What is the most common natural problem found in embankment? | 
| A. | Settlement | 
| B. | Stability of foundation | 
| C. | Stability of slope | 
| D. | Soil erosion | 
| Answer» E. | |
| 9. | An embankment is classified as high if height exceeds __________ | 
| A. | 3.0 m | 
| B. | 4.0 m | 
| C. | 5.0 m | 
| D. | 6.0 m | 
| Answer» D. 6.0 m | |
| 10. | Stability of slopes change with __________ | 
| A. | Climate | 
| B. | Increase in load | 
| C. | Increase in soil | 
| D. | Increase in width of pavement | 
| Answer» C. Increase in soil | |
| 11. | The stability of foundation is checked to ensure __________ | 
| A. | Lateral strength | 
| B. | Compressive strength | 
| C. | Shear strength | 
| D. | Tensile strength | 
| Answer» D. Tensile strength | |
| 12. | The settlement is due to __________ | 
| A. | More compaction | 
| B. | Inadequate compaction | 
| C. | Temperature | 
| D. | Air pressure | 
| Answer» C. Temperature | |
| 13. | The fill material used in embankment is __________ | 
| A. | Peat | 
| B. | Silt | 
| C. | Clay | 
| D. | Granular soils | 
| Answer» E. | |
| 14. | If the height of embankment increases __________ | 
| A. | Slope stability increases | 
| B. | Slope stability remains constant | 
| C. | Slope has to reduced | 
| D. | Slopes need to be flattered | 
| Answer» E. | |
| 15. | What is the last step in design of embankment? | 
| A. | Height | 
| B. | stability of slope | 
| C. | Stability of foundation | 
| D. | Settlement | 
| Answer» C. Stability of foundation | |
| 16. | THE_CONSOLIDATION_CAN_BE_ACHIEVED_FASTER_BY?$ | 
| A. | Clay | 
| B. | Peat | 
| C. | Sand drains | 
| D. | Sand filter | 
| Answer» D. Sand filter | |
| 17. | The liquid limit of soil for embankment construction is$ | 
| A. | Less than 70% | 
| B. | Less than 90% | 
| C. | Less than 60% | 
| D. | Less than 45% | 
| Answer» B. Less than 90% | |
| 18. | The minimum spacing between the two sand beds is$ | 
| A. | 1.0 m | 
| B. | 1.5 m | 
| C. | 2.0 m | 
| D. | 2.5 m | 
| Answer» E. | |
| 19. | The rollers that uses both tamping and kneading is | 
| A. | Plain roller | 
| B. | Vibratory roller | 
| C. | Sheep foot roller | 
| D. | Pneumatic roller | 
| Answer» D. Pneumatic roller | |
| 20. | The plasticity index for a sub grade should be less than | 
| A. | 45 | 
| B. | 35 | 
| C. | 25 | 
| D. | 15 | 
| Answer» D. 15 | |
| 21. | The free swelling index of soil should be less than | 
| A. | 50 | 
| B. | 60 | 
| C. | 70 | 
| D. | 80 | 
| Answer» B. 60 | |
| 22. | The investigation of embankment should be carried out fo? | 
| A. | Twice the height of embankment | 
| B. | Thrice the height of embankment | 
| C. | Exact height of embankment | 
| D. | Half height of embankment | 
| Answer» B. Thrice the height of embankment | |
| 23. | The most common natural problem found in embankment is | 
| A. | Settlement | 
| B. | Stability of foundation | 
| C. | Stability of slope | 
| D. | Soil erosion | 
| Answer» E. | |
| 24. | An embankment is classified as high if height exceeds | 
| A. | 3.0 m | 
| B. | 4.0 m | 
| C. | 5.0 m | 
| D. | 6.0 m | 
| Answer» D. 6.0 m | |
| 25. | Stability of slopes change with | 
| A. | Climate | 
| B. | Increase in load | 
| C. | Increase in soil | 
| D. | Increase in width of pavement | 
| Answer» C. Increase in soil | |
| 26. | The stability of foundation is checked to ensure | 
| A. | Lateral strength | 
| B. | Compressive strength | 
| C. | Shear strength | 
| D. | Tensile strength | 
| Answer» D. Tensile strength | |
| 27. | The settlement is due to | 
| A. | More compaction | 
| B. | Inadequate compaction | 
| C. | Temperature | 
| D. | Air pressure | 
| Answer» C. Temperature | |
| 28. | The fill material used in embankment is | 
| A. | Peat | 
| B. | Silt | 
| C. | Clay | 
| D. | Granular soils | 
| Answer» E. | |
| 29. | If the height of embankment increases | 
| A. | Slope stability increases | 
| B. | Slope stability remains constant | 
| C. | Slope has to reduced | 
| D. | Slopes need to be flattered | 
| Answer» E. | |
| 30. | The last step in design of embankment is | 
| A. | Height | 
| B. | stability of slope | 
| C. | Stability of foundation | 
| D. | Settlement | 
| Answer» C. Stability of foundation | |