451. |
__The deductions for, employees provident fund start__ |
A. | Immediately on joining the service |
B. | After 60 days of joining the service |
C. | After 100 days of joining the service |
D. | After 240 days of joining the service |
Answer» E. | |
452. |
__A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is__ |
A. | 0.50 |
B. | 0.66 |
C. | 0.84 |
D. | 0.95 |
Answer» D. 0.95 | |
453. |
__The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as__ |
A. | Duration |
B. | Total float |
C. | Free float |
D. | Interfering float |
Answer» D. Interfering float | |
454. |
__Product layout is employed for__ |
A. | Batch production |
B. | Continuous production |
C. | Effective utilization of machine |
D. | All of the above |
Answer» C. Effective utilization of machine | |
455. |
__Emergency rush order can be pushed more effectively in__ |
A. | Job production |
B. | Automatic production |
C. | Continuous production |
D. | Intermittent production |
Answer» E. | |
456. |
__Which of the following plans motivates supervisors by paying a premium on time saved by workers?__ |
A. | Halsey plan |
B. | Rowan plan |
C. | Haynes plan |
D. | Emerson's plan |
Answer» D. Emerson's plan | |
457. |
__Break-even analysis can be used for__ |
A. | Short run analysis |
B. | Long run analysis |
C. | Average of above two run analysis |
D. | There is no such criterion |
Answer» B. Long run analysis | |
458. |
__Routing__ |
A. | Prescribes the sequence of operations to be followed |
B. | Determines the programme for the operations |
C. | Is concerned with starting of processes |
D. | Regulates the progress of job through various processes |
Answer» B. Determines the programme for the operations | |
459. |
__Gantt chart provides information about the__ |
A. | Material handling |
B. | Proper utilization of manpower |
C. | Production schedule |
D. | Efficient working of machine |
Answer» D. Efficient working of machine | |
460. |
__According to Muther, the basic principle of best layout is__ |
A. | Principle of overall integration |
B. | Principle of flow |
C. | Principle of flexibility |
D. | All of these |
Answer» E. | |
461. |
__PERT__ |
A. | Provides an approach for keeping planning up-to-date |
B. | Provides a way for management to require that planning be done on a uniform and logical basis |
C. | Permits management to foresee quickly the impact of variations from the plan |
D. | All of the above |
Answer» E. | |
462. |
__A-B-C analysis__ |
A. | Is a basic technique of materials management |
B. | Is meant for relative inventory control |
C. | Does not depend upon the unit cost of the item but on its annual consumption |
D. | All of the above |
Answer» E. | |
463. |
__Work study is done with the help of__ |
A. | Process chart |
B. | Material handling |
C. | Stop watch |
D. | All of the above |
Answer» D. All of the above | |
464. |
__Gantt charts are used for__ |
A. | Forecasting sales |
B. | Production schedule |
C. | Scheduling and routing |
D. | Linear programming |
Answer» C. Scheduling and routing | |
465. |
__The interchangeability can be achieved by__ |
A. | Standardization |
B. | Better process planning |
C. | Bonus plan |
D. | Better product planning |
Answer» B. Better process planning | |
466. |
_Standard time is equal to$? |
A. | (Normal time) - (allowances) |
B. | (Normal time) + (allowances) |
C. | Representative time multiplied by rating factor |
D. | Normal time taken by an operation |
Answer» C. Representative time multiplied by rating factor | |
467. |
_Job evaluation is the method of determining the$? |
A. | Relative worth of jobs |
B. | Skills required by a worker |
C. | Contribution of a worker |
D. | Contribution of a job |
Answer» B. Skills required by a worker | |
468. |
_The most important function of inventory control is$? |
A. | Stock control system |
B. | To run the stores effectively |
C. | Technical responsibility for the state of materials |
D. | All of the above |
Answer» E. | |
469. |
_Basic motion time study gives times for basic motions in ten thousandths of$? |
A. | Second |
B. | Minute |
C. | Hour |
D. | Day |
Answer» C. Hour | |
470. |
_String diagram is used when$? |
A. | Team of workers is working at a place |
B. | Material handling is to be done |
C. | Idle time is to be reduced |
D. | All of the above |
Answer» B. Material handling is to be done | |
471. |
_In micro-motion study, therblig is described by$? |
A. | A symbol |
B. | An event |
C. | An activity |
D. | Standard symbol and colour |
Answer» E. | |
472. |
_The linear programming techniques can be applied successfully to industries like$? |
A. | Iron and steel |
B. | Food processing |
C. | Oil and chemical |
D. | All of the above |
Answer» E. | |
473. |
_Pessimistic time is$? |
A. | The maximum time which an activity might require |
B. | The average time required for a job |
C. | The most probable time considering all conditions |
D. | The minimum time in which an activity can possibly be accomplished |
Answer» B. The average time required for a job | |
474. |
_Templates are used for$? |
A. | A planning layout |
B. | Flow of material |
C. | Advancing a programme in automatic machines |
D. | Copying complicated profiles |
Answer» B. Flow of material | |
475. |
_Travel charts provide$? |
A. | An idea of the flow of materials at various stages |
B. | A compact estimate of the handling which must be done between various work sections |
C. | The information for changes required in rearranging material handling equipment |
D. | An approximate estimate of the handling which must be done at a particular station |
Answer» C. The information for changes required in rearranging material handling equipment | |
476. |
_The main disadvantage of line organisation is$? |
A. | Top level executives have to do excessive work |
B. | Structure is rigid |
C. | Communication delays occur |
D. | All of the above |
Answer» E. | |
477. |
_Time study is carried out$? |
A. | By finding all the significant informations regarding the job, work place and machine tool etc |
B. | By breaking up each operation into small elements which are measurable with the help of the measuring device accurately |
C. | By observing and recording the time taken by the operator for an operation |
D. | All of the above |
Answer» E. | |
478. |
_Linear programming can be applied successfully to$? |
A. | Chemical industry |
B. | Oil industry |
C. | Banks |
D. | All of these |
Answer» E. | |
479. |
_CPM requires$? |
A. | Single time estimate |
B. | Double time estimate |
C. | Triple time estimate |
D. | None of these |
Answer» B. Double time estimate | |
480. |
_Gantt chart is used for$? |
A. | Inventory control |
B. | Material handling |
C. | Production schedule |
D. | Machine repair schedules |
Answer» D. Machine repair schedules | |
481. |
_The process layout is best suited where$? |
A. | Specialization exists |
B. | Machines are arranged according to sequence of operation |
C. | Few number of non-standardized units is to be produced |
D. | Mass production is envisaged |
Answer» D. Mass production is envisaged | |
482. |
_Process layout is employed$? |
A. | Where low volume of production is required |
B. | Where similar jobs are manufactured on similar machines |
C. | Where machines are arranged on functional basis |
D. | All of the above |
Answer» E. | |
483. |
_Time study is used to$? |
A. | Determine standard costs |
B. | Determine the number of machines a person may run |
C. | Provide a basis for setting piece price or incentive wages |
D. | All of the above |
Answer» E. | |
484. |
_Monte Carlo solutions in queuing theory are extremely useful in queuing problems$? |
A. | That can't be analysed mathematically |
B. | Involving multistage queuing |
C. | To verify mathematical results |
D. | All of the above |
Answer» B. Involving multistage queuing | |
485. |
_Which of the following organizations is best suited for steel plants$? |
A. | Functional organization |
B. | Line organization |
C. | Staff organization |
D. | Line, staff and functional organizations |
Answer» E. | |
486. |
_In break even analysis, total cost consists of$? |
A. | Fixed cost + sales revenue |
B. | Variable cost + sales revenue |
C. | Fixed cost + variable cost |
D. | Fixed cost + variable cost + profit |
Answer» D. Fixed cost + variable cost + profit | |
487. |
_According to Rowan plan of wage incentive system, bonus is paid to a worker$? |
A. | Whose output exceeds 67% efficiency |
B. | On the percentage of time saved |
C. | On the percentage of time worked |
D. | On the percentage of standard time |
Answer» D. On the percentage of standard time | |
488. |
_Which of the following are the guidelines for the construction of a network diagram?$? |
A. | Each activity is represented by one and only one arrow in the network |
B. | Dangling must be avoided in a network diagram |
C. | Dummy activity consumes no time or resource |
D. | All of the above |
Answer» E. | |
489. |
_Which one of the following chart gives simultaneously information about the progress of work and machine loading?$? |
A. | Process chart |
B. | Machine load chart |
C. | Man-machine chart |
D. | Gantt chart |
Answer» D. Gantt chart | |
490. |
_Product layout is also known as$? |
A. | Analytical layout |
B. | Synthetic layout |
C. | Static product layout |
D. | None of these |
Answer» C. Static product layout | |
491. |
_The technique for establishing and maintaining priorities among the various jobs of any project is known as$? |
A. | Event flow scheduling technique |
B. | Critical ratio scheduling |
C. | Slotting technique for scheduling |
D. | Short interval scheduling |
Answer» C. Slotting technique for scheduling | |
492. |
_An event is indicated on the network by$? |
A. | A straight line |
B. | A number enclosed in a circle or a square |
C. | A straight line with circles at the ends |
D. | A dotted line |
Answer» C. A straight line with circles at the ends | |
493. |
_A graphical device used to determine the break-even point and profit potential under varying conditions of output and costs, is known as$? |
A. | Gantt chart |
B. | Flow chart |
C. | Break-even chart |
D. | PERT chart |
Answer» D. PERT chart | |
494. |
_PERT$? |
A. | Provides an approach for keeping planning up-to-date |
B. | Provides a way for management to require that planning be done on a uniform and logical basis |
C. | Permits management to foresee quickly the impact of variations from the plan |
D. | All of the above |
Answer» E. | |
495. |
_PERT stands for$? |
A. | Program Estimation and Reporting Technique |
B. | Process Estimation and Review Technique |
C. | Program Evaluation and Review Technique |
D. | Planning Estimation and Resulting Technique |
Answer» D. Planning Estimation and Resulting Technique | |
496. |
_The disadvantage of product layout is$? |
A. | High initial investment for the specialized facilities |
B. | Skilled labour to operate machines |
C. | Production time is longer, requiring more goods in inventory |
D. | High cost of inspection |
Answer» B. Skilled labour to operate machines | |
497. |
_In inventory control, the economic order quantity is the$? |
A. | Optimum lot size |
B. | Highest level of inventory |
C. | Lot corresponding to break-even point |
D. | Capability of a plant to produce |
Answer» B. Highest level of inventory | |
498. |
According to MAPI formula, the old machine should be replaced by new one when (Here, CAM = Challenger's Adverse minimum, DAM = Defender's Adverse minimum)$? |
A. | CAM < DAM |
B. | CAM > DAM |
C. | CAM = DAM |
D. | There is no such criterion |
Answer» B. CAM > DAM | |
499. |
One of the basic essentials of an incentive plan is that$? |
A. | A differential piece rate system should exist |
B. | Minimum wages should be guaranteed |
C. | Provide incentive to group efficiency performance |
D. | All standards should be based on time studies |
Answer» E. | |
500. |
Breakeven analysis is a$? |
A. | Short term analysis |
B. | Long term analysis |
C. | Average of short and long term analysis |
D. | Any one of these |
Answer» B. Long term analysis | |