                                    _Pessimistic time is$? | 
                            
| A. | The maximum time which an activity might require | 
| B. | The average time required for a job | 
| C. | The most probable time considering all conditions | 
| D. | The minimum time in which an activity can possibly be accomplished | 
| Answer» B. The average time required for a job | |