The drawing for re alignment shows the existing road, proposed re alignment, contours and all other features it is called as ___________ |
| A. | Plan |
| B. | Elevation |
| C. | Cross section |
| D. | Longitudinal section |
| Answer» B. Elevation | |
| 2. |
Embankments are provided on a highway near ___________ |
| A. | Important cities |
| B. | Religious structure |
| C. | Railway tracks and highly flooded area |
| D. | Costly structures |
| Answer» D. Costly structures | |
| 3. |
The highly flooded areas should be re aligned by ___________ |
| A. | Providing additional thickness of the pavement |
| B. | Providing suitable layers of pavement |
| C. | Providing appropriate camber |
| D. | Providing higher geometric specifications |
| Answer» B. Providing suitable layers of pavement | |
| 4. |
To minimize the cost of the project the most suitable method is ___________ |
| A. | CPM |
| B. | PERT |
| C. | CPM and PERT |
| D. | Normal distribution curves |
| Answer» B. PERT | |
| 5. |
Road roughness is tested by ___________ |
| A. | Bump integrator |
| B. | RTRRMS |
| C. | GIS |
| D. | UI |
| Answer» B. RTRRMS | |
| 6. |
Inspection of the site is done in which survey? |
| A. | Preliminary |
| B. | Secondary |
| C. | Reconnaissance |
| D. | Final report |
| Answer» D. Final report | |
| 7. |
A part of land that is acquired during the initial stages of construction for future expansion is called ____________ |
| A. | Kerb |
| B. | Footpath |
| C. | Right of way |
| D. | Camber |
| Answer» D. Camber | |
| 8. |
The drawing for re alignment shows the existing road, proposed re alignment, contours and all other features it is called a? |
| A. | Plan |
| B. | Elevation |
| C. | Cross section |
| D. | Longitudinal section |
| Answer» B. Elevation | |
| 9. |
Embankments are provided on highway near |
| A. | Important cities |
| B. | Religious structure |
| C. | Railway tracks and highly flooded area |
| D. | Costly structures |
| Answer» D. Costly structures | |
| 10. |
The highly flooded areas should be re aligned by |
| A. | Providing additional thickness of pavement |
| B. | Providing suitable layers of pavement |
| C. | Providing appropriate camber |
| D. | Providing higher geometric specifications |
| Answer» B. Providing suitable layers of pavement | |
| 11. |
To minimize the cost of the project the most suitable method is |
| A. | CPM |
| B. | PERT |
| C. | CPM and PERT |
| D. | Normal distribution curves |
| Answer» B. PERT | |
| 12. |
Road roughness is tested by |
| A. | Bump integrator |
| B. | RTRRMS |
| C. | GIS |
| D. | UI |
| Answer» B. RTRRMS | |
| 13. |
Inspection of site is done in which survey? |
| A. | Preliminary |
| B. | Secondary |
| C. | Reconnaissance |
| D. | Final report |
| Answer» D. Final report | |
| 14. |
Which method is recommended by IRC for flexible pavements? |
| A. | CBR |
| B. | IRC 6 |
| C. | IRC 21 |
| D. | IRC 58 |
| Answer» B. IRC 6 | |
| 15. |
A part of land that is acquired during initial stages of construction for future expansion is called |
| A. | Kerb |
| B. | Footpath |
| C. | Right of way |
| D. | Camber |
| Answer» D. Camber | |