| 1. |
The compaction of sand is done by __________ |
| A. | Rollers |
| B. | Animals |
| C. | Vibrator |
| D. | Jetting |
| Answer» E. | |
| 2. |
The stiff materials can be excavated by __________ |
| A. | Dragline |
| B. | Hoe |
| C. | Power shovel |
| D. | Scrapper |
| Answer» C. Power shovel | |
| 3. |
Dragline cannot excavate __________ |
| A. | Soft rocks |
| B. | Black cotton soil |
| C. | Clay |
| D. | Stiff material |
| Answer» E. | |
| 4. |
The boom is supported by __________ |
| A. | Cab |
| B. | Dipper stick |
| C. | Hoist line |
| D. | Crawler |
| Answer» D. Crawler | |
| 5. |
The precise control of excavation is possible by __________ |
| A. | Scrapper |
| B. | Hoe |
| C. | Shovel |
| D. | Bulldozer |
| Answer» B. Hoe | |
| 6. |
The blade angle of bulldozer is usually __________ |
| A. | 60 |
| B. | 90 |
| C. | 15 |
| D. | 45 |
| Answer» C. 15 | |
| 7. |
The best time to remove soil is during __________ |
| A. | Summer |
| B. | Winter |
| C. | Rainy season |
| D. | During storm |
| Answer» B. Winter | |
| 8. |
The removal of earth for highway formation is __________ |
| A. | Embankment |
| B. | Sub grade |
| C. | Excavation |
| D. | Filling |
| Answer» D. Filling | |