1.

The measurement is made for stone work in square metre in case of ________

A. Wall facing
B. Columns, lintels, copings
C. Footings
D. Building work
Answer» B. Columns, lintels, copings
2.

The floor area includes the area of the balcony up to _________

A. 50 %
B. 60 %
C. 70 %
D. 45 %
Answer» B. 60 %
3.

Referring to the figure below, pick up the correct statement from the following.

A. The total length of centre line of four walls is 20 m
B. Length of long wall out-to-out is 6.80 m
C. Length of short walls in-to-in is 3.20 m
D. Total length of four wall – 20 m, length of short wall – 6.8 m
Answer» E.
4.

The ‘centre line method’ is specially adopted for estimating?

A. Circular buildings
B. Hexagonal buildings
C. Other geometrical shaped buildings
D. Circular, hexagonal and other geometric shapes
Answer» E.
5.

The floor area includes the area of the balcony up to ________?

A. 50 %
B. 60 %
C. 70 %
D. 45 %
Answer» B. 60 %
6.

The expected out turn of half brick partition wall per mason per day is _________

A. 1.5 m<sup>3</sup>
B. 2.0 m<sup>3</sup>
C. 4.0 m<sup>2</sup>
D. 5.0 m<sup>2</sup>
Answer» B. 2.0 m<sup>3</sup>
7.

The expected out turn for earth work in excavation in ordinary soil per labourer per day is _____

A. 1 cum
B. 2 cum
C. 3 cum
D. 4 cum
Answer» E.
8.

The total length of centre line of four walls is 20 m

A. Length of long wall out-to-out is 6.80 m
B. Length of short walls in-to-in is 3.20 m
C. Total length of four wall – 20 m, length of short wall – 6.8 m
Answer» D.
9.

The ‘centre line method’ is specially adopted for estimating?$

A. Circular buildings
B. Hexagonal buildings
C. Other geometrical shaped buildings
D. Circular, hexagonal and other geometric shapes
Answer» E.
10.

For the construction of buildings, the subheads of the estimate are ________

A. Earthwork, Concrete work, Brick work
B. Plastering or pointing, finishing, water supply and sanitary work
C. Brickwork Flooring, Wood work, Steel work
D. Earthwork, concrete work, brick work, plastering, water supply and steel work
Answer» E.
11.

For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is _______

A. 0.90 m<sup>3</sup>
B. 0.94 m<sup>3</sup>
C. 0.98 m<sup>3</sup>
D. 0.98 m<sup>3</sup>
Answer» C. 0.98 m<sup>3</sup>