The expected out turn of half brick partition wall per mason per day is _________ |
A. | 1.5 m<sup>3</sup> |
B. | 2.0 m<sup>3</sup> |
C. | 4.0 m<sup>2</sup> |
D. | 5.0 m<sup>2</sup> |
Answer» B. 2.0 m<sup>3</sup> | |