Explore topic-wise MCQs in Testing Subject.

This section includes 657 Mcqs, each offering curated multiple-choice questions to sharpen your Testing Subject knowledge and support exam preparation. Choose a topic below to get started.

1.

…………………………report is a document wherein all the details obtained fromtechnical analysis, financial analysis, profitability analysis etc. are put together.

A. feasibility
B. project
C. both
D. none
Answer» D. none
2.

Reject a project if it’s IRR is……………….when compared to desired minimum

A. higher
B. lower
C. negative
D. positive
Answer» C. negative
3.

Under Net Terminal Value Method, accept a project if it’s NTV is……………………

A. higher
B. lower
C. negative
D. positive
Answer» E.
4.

In independent projects, accept a project if it’s NPV is………………………..

A. higher
B. lower
C. negative
D. positive
Answer» E.
5.

The process of measuring the progress and performance of a project is called:

A. project appraisal.
B. project evaluation.
C. project control.
D. project audit.
Answer» C. project control.
6.

In case of mutually exclusive projects, the project with ……………. PI is to beselected.

A. higher
B. lower
C. negative
D. positive
Answer» B. lower
7.

The excess of the present value over the cost of the project is ……………………..

A. irr
B. arr
C. npv
D. ntv
Answer» E.
8.

For discounted cash flow methods, the discount rate used is:

A. fixed arbitrarily
B. equivalent to bank rate.
C. equivalent to firm’s average cost of capital.
D. equivalent to final rate of dividend.
Answer» D. equivalent to final rate of dividend.
9.

The scientific technique of evaluation of capital expenditure decisions includethe following except:

A. npv.
B. pi.
C. irr.
D. payback period.
Answer» E.
10.

The difference between the total present value of a stream of cash flows of agiven rate of discount and the initial capital outlay is known as the :

A. irr.
B. arr.
C. npv.
D. net profit.
Answer» D. net profit.
11.

Profitability index shows benefits from the proposal in :

A. absolute terms.
B. relative terms.
C. both of the above.
D. none of these.
Answer» C. both of the above.
12.

Which one of the following is not a discounted cash flow technique:

A. arr
B. irr
C. npv
D. pi
Answer» B. irr
13.

The discount rate must be determined in advance for the :

A. payback period.
B. time adjusted rate of return method.
C. irr
D. npv method.
Answer» E.
14.

Which one is not an element of project appraisal:

A. technical feasibility.
B. network analysis.
C. economical viability.
D. commercial viability.
Answer» C. economical viability.
15.

Project appraisal is done by:

A. government.
B. financial institution only.
C. entrepreneur only.
D. both financial institution and entrepreneur.
Answer» E.
16.

Project…………………………… is done after the project is implemented.

A. management
B. appraisal
C. evaluation
D. none
Answer» D. none
17.

The main object of project appraisal is:

A. to find whether the project is technically feasible.
B. to ascertain whether the project is financially feasible.
C. to decide whether to accept or reject a project.
D. to know whether the project is eco-friendly.
Answer» D. to know whether the project is eco-friendly.
18.

The discount rate at which present value of cash inflows equals to the presentvalue of cash outflows is called …………………..

A. arr
B. irr
C. ntv
D. urgency
Answer» C. ntv
19.

…………………. is also called trial and error Method.

A. arr
B. irr
C. ntv
D. urgency
Answer» C. ntv
20.

Original investment is divided by constant cash……………………….. to get paybackperiod.

A. inflows
B. outflows
C. balance
D. both (a)and (b)
Answer» B. outflows
21.

NPV, PI and ………………………. are the three discounted cash flow techniques.

A. arr
B. irr
C. ntv
D. urgency
Answer» C. ntv
22.

Payback period and ARR methods are …………………..

A. traditional
B. discounting
C. modern
D. none
Answer» B. discounting
23.

Profitability index is also known as ……………………………….ratio

A. roi
B. benefit- cost
C. debt-equity
D. none
Answer» C. debt-equity
24.

Project appraisal is the process of estimating the costs and benefits of a projectto arrive at the ………………………decision.

A. investment
B. profitability
C. liquidity
D. none of these
Answer» B. profitability
25.

Project appraisal is usually done by a ………………………….. Institution.

A. marketing
B. financial
C. production
D. none of these
Answer» C. production
26.

..……is a contract between the owner and user of the asset to use the asset for aconsideration.

A. venture capital
B. layered financing
C. deferred credit
D. lease financing
Answer» E.
27.

Arrangement where payments to suppliers are made in agreed installments over a specified period of time at some agreed rate of interest on the outstandingbalance.

A. venture capital
B. layered financing
C. deferred credit
D. lease financing
Answer» D. lease financing
28.

Giving capital to enterprise that has risk and adventure is called………………………

A. venture capital
B. layered financing
C. deferred credit
D. lease financing
Answer» B. layered financing
29.

Raising capital from multiple sources is known as…………………….

A. venture capital
B. layered financing
C. deferred credit
D. lease financing
Answer» C. deferred credit
30.

………………. Is also known as marginal profit ratio

A. p/v
B. current
C. profitability
D. none
Answer» B. current
31.

Contribution margin ratio is better known as……………..

A. p/v
B. current
C. profitability
D. none
Answer» B. current
32.

…………………..ratio establishes relationship between contribution margin andtotal sales.

A. p/v
B. current
C. profitability
D. none
Answer» B. current
33.

……………………… is described as bread earning point.

A. cash flow
B. fund flow
C. ratio
D. breakeven
Answer» E.
34.

…………………… is an equilibrium point.

A. cash flow
B. fund flow
C. ratio
D. breakeven
Answer» E.
35.

Mathematical relationship between two figures taken from financial statementsis called……….

A. cash flow
B. fund flow
C. ratio
D. breakeven
Answer» D. breakeven
36.

Which of the following is not a technique of financial analysis:

A. ratio analysis.
B. risk analysis.
C. cash flow analysis.
D. fund flow analysis.
Answer» C. cash flow analysis.
37.

……….shows movement of cash into and out of the firm and its net effect onbalance sheet.

A. cash flow
B. fund flow
C. ratio
D. breakeven
Answer» B. fund flow
38.

…………shows the changes in assets, liabilities and net worth between twobalance sheet dates.

A. cash flow
B. fund flow
C. ratio
D. breakeven
Answer» C. ratio
39.

Estimated time required in normal conditions complete an activity is ………………

A. pessimistic time
B. optimistic time
C. most likely time
D. none of these
Answer» D. none of these
40.

Maximum possible time to complete an activity is ………………………

A. pessimistic time
B. optimistic time
C. most likely time
D. none of these
Answer» B. optimistic time
41.

Which of the following is not a network technique :

A. cpm.
B. pert.
C. swot.
D. lob.
Answer» D. lob.
42.

Shortest possible time to complete an activity is ………………………

A. pessimistic time
B. optimistic time
C. most likely time
D. none of these
Answer» C. most likely time
43.

Decision regarding factory design is part of :

A. network analysis.
B. financial analysis.
C. technical analysis.
D. social cost benefit analysis.
Answer» D. social cost benefit analysis.
44.

Which of the following is a technique of project identification:

A. desk research.
B. sensitivity analysis.
C. cvp analysis.
D. none of these.
Answer» B. sensitivity analysis.
45.

Which of the following is not a phase in the project life cycle:

A. pre- investment phase.
B. construction phase.
C. normalization phase.
D. growth phase.
Answer» E.
46.

……………………… study is a systematic method adopted to find out the possibilityand practicability of starting a project.

A. profitability
B. liquidity
C. feasibility
D. viability
Answer» D. viability
47.

………………………… is the difference between the actual sales and break even sales.

A. margin of safety
B. fixed cost
C. contribution
D. profit
Answer» B. fixed cost
48.

Difference between latest finish time and estimated time to perform the projectis called………..

A. eft
B. lst
C. lft
D. est
Answer» C. lft
49.

The latest possible time an activity can finish without delaying the project is called…….

A. eft
B. lst
C. lft
D. est
Answer» D. est
50.

The sum of earliest start time and estimated time to perform the project is called……..

A. eft
B. lst
C. lft
D. est
Answer» B. lst