

MCQOPTIONS
Saved Bookmarks
This section includes 18 Mcqs, each offering curated multiple-choice questions to sharpen your Civil Engineering knowledge and support exam preparation. Choose a topic below to get started.
1. |
A large work or project may consists of several building or small works and each of these work is known as ___________ |
A. | sub-work |
B. | sub-project |
C. | sub-head |
D. | sub-construction |
Answer» B. sub-project | |
2. |
________________ is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate. |
A. | Prime cost |
B. | Provisional sum |
C. | Capital cost |
D. | Building cost index |
Answer» C. Capital cost | |
3. |
__________ is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality. |
A. | Cube Rate Estimate |
B. | Supplementary Estimate |
C. | Maintenance Estimate |
D. | Plinth Area Estimate |
Answer» E. | |
4. |
Approximate cost of sewerage project for a population of one [email protected] Rs. 10/- head works out as Rs. 10 lakh. |
A. | True |
B. | False |
Answer» C. | |
5. |
FOR_STOREYED_BUILDING_PLINTH_AREA_ESTIMATE_IS_NOT_PREPARED_FOR_EACH_STOREY_SEPARATELY.?$ |
A. | True |
B. | False |
Answer» C. | |
6. |
________________is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate.$ |
A. | Prime cost |
B. | Provisional sum |
C. | Capital cost |
D. | Building cost index |
Answer» C. Capital cost | |
7. |
__________ is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality.$ |
A. | Cube Rate Estimate |
B. | Supplementary Estimate |
C. | Maintenance Estimate |
D. | Plinth Area Estimate |
Answer» E. | |
8. |
The term ______________ is used to denote a procedure of costing or valuing an item of work on the basis of actual labourers and materials required. |
A. | prime cost |
B. | hour-work |
C. | day-work |
D. | sub-work |
Answer» D. sub-work | |
9. |
A large work or project may consists of several building or small works and each of these work is known as___________ |
A. | sub-work |
B. | sub-project |
C. | sub-head |
D. | sub-construction |
Answer» B. sub-project | |
10. |
_______________ estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition. |
A. | Supplementary and revised estimate |
B. | Maintenance estimate |
C. | Item rate estimate |
D. | Revised estimate |
Answer» C. Item rate estimate | |
11. |
In this method approx. total length of walls is found in running metre and this total length multiplied by the rate per running metre of wall gives a fairly accurate cost. |
A. | Annual repair |
B. | Item rate estimate |
C. | Approximate quantity method estimate |
D. | Cubical content estimate |
Answer» D. Cubical content estimate | |
12. |
Cube rate estimate is less accurate as compared to the plinth area estimate as the height of the building is also compared? |
A. | False |
B. | True |
Answer» C. | |
13. |
Approx. cost of a bridge of 3 spans of 50 m each span @Rs.30000/- per running m of span comes to 3*50*30000= Rs. 45 lakhs. |
A. | True |
B. | False |
Answer» B. False | |
14. |
The approx. cost of 10 km length of irrigation channel of 3 cu m per sec. capacity @ Rs.70000/- per km works out as Rs.7 lakh. |
A. | True |
B. | False |
Answer» B. False | |
15. |
Per kilometre basis depending on the nature of road, for 10 km of a state highway approx. cost @ Rs. 50000/- per 1 km works out as Rs. 5 lakh. |
A. | True |
B. | False |
Answer» C. | |
16. |
Approximate cost of a hostel building for 100 students @Rs.10000/- per student works out as Rs. 10 lakhs. |
A. | True |
B. | False |
Answer» B. False | |
17. |
_________________ is required for preliminary studies of various aspects of a work or project. |
A. | Supplementary Estimate |
B. | Plinth Area Estimate |
C. | Revised Estimate |
D. | Abstract Estimate |
Answer» E. | |
18. |
To make out an estimate for a work the following data are necessary-Drawing, Specification and ___________ |
A. | materials |
B. | rates |
C. | labours |
D. | transportation |
Answer» C. labours | |