51. |
In a PERT/CPM network, computing the critical path requires |
A. | determining the total project duration |
B. | assigning the earliest finish time for an activity as the earliest start time for the next |
C. | that the latest finishing time for an activity not delay the overall project beyond initial expectation |
D. | a sophisticated and complex computer program |
Answer» C. that the latest finishing time for an activity not delay the overall project beyond initial expectation | |
52. |
Which of the following is the sequence of operations through which product must pass |
A. | Scheduling |
B. | Critical path |
C. | Transformation path |
D. | Routing |
Answer» E. | |
53. |
A process layout would be most appropriate in which of the following cases |
A. | Constructing a Boeing 777 air craft |
B. | A fast food restaurant |
C. | An automobile factory |
D. | A garment restaurant |
Answer» E. | |
54. |
The operating characteristic (OC) curve shows the probability of |
A. | rejection for every possible true percentage of defectives |
B. | acceptance for every possible true percentage of defectives |
C. | making type I errors for various percentages of defectives |
D. | none of the above |
Answer» C. making type I errors for various percentages of defectives | |
55. |
A planning systems that schedules the precise quantity of materials needed to make a product is called |
A. | Flexible scheduling |
B. | Cycle time arrangement |
C. | Materials requirements planning |
D. | Economic order quantities |
Answer» D. Economic order quantities | |
56. |
The raw materials , components , completed or partially completed products ,and pieces of equipment a firm uses are often referred to as |
A. | Inventory |
B. | Order quantities |
C. | Production |
D. | Outputs |
Answer» B. Order quantities | |
57. |
Which one of the following is a concern expressed by suppliers ? |
A. | Elimination of in plant inventory |
B. | Delivery to the point of use |
C. | Production with zero defects |
D. | Large lot sizes |
Answer» D. Large lot sizes | |
58. |
Which of the following chart will indicate only the cumulative workloads for each job and to what extent the work centers are to be scheduled? |
A. | Flowchart |
B. | Gantt chart |
C. | Gantt progress chart |
D. | CPM chart |
Answer» C. Gantt progress chart | |
59. |
In basic EOQ model if the cost of placing an order doubles and all other values remain constant the EOQ will |
A. | Increase by about 41% |
B. | Increase by100% |
C. | Increase by200% |
D. | Either increase or decrease |
Answer» B. Increase by100% | |
60. |
Which of the following options are controlling functions of a manufacturing organization? 1. Estimating 2. Routing 3. Dispatching 4. Expediting |
A. | Options 1 & 2 |
B. | Options 2 & 3 |
C. | Options 3 & 4 |
D. | Options 1 & 4 |
Answer» D. Options 1 & 4 | |
61. |
Which of the following quality control tools helps in pin-pointing the exact points at which errors have crept in? |
A. | Histogram |
B. | Flow chart |
C. | Scatter diagram |
D. | Control charts |
Answer» E. | |
62. |
Decisions include facility planning, location and layout. |
A. | Operating |
B. | Technology |
C. | Capacity |
D. | Quality |
Answer» D. Quality | |
63. |
What technique deals with the problem of supplying sufficient facilities to production lines or individuals that require uneven service? |
A. | Supply-demand theory |
B. | PERT |
C. | Inventory theory |
D. | Queuing theory |
Answer» E. | |
64. |
The so-called ‘quality qurus’ of Total Quality Management (TQM) do not include one of the following |
A. | Kavoru ishikawa |
B. | Joseph M juran |
C. | Bill coshy |
D. | W.Edward Deming |
Answer» D. W.Edward Deming | |
65. |
________________ provides wider latitude towards the project team for balancing that dimension against the other four. |
A. | Degree of freedom |
B. | Driver |
C. | Constraint |
D. | SDider chart |
Answer» B. Driver | |
66. |
ABC analysis is based upon the principal that |
A. | All items in inventory must be monitored very closely |
B. | These are very usually a few critical items zmd many items which are less critical |
C. | An item is critical if its usage is high |
D. | The safety stock in terms of volume should be higher for a items than for items |
Answer» C. An item is critical if its usage is high | |
67. |
A quality circle is composed of a small group of employees who genuinely care about others and who preferably do work that includes which of the following? 1 Meeting voluntarily with a leader on a regular basis 2. Identifying the problems 3 Balancing operations in assembly line 4 Setting up productivity norms and evaluation of production operations |
A. | Options 1 & 4 |
B. | Options 1 & 2 |
C. | Options 1 & 3 |
D. | Options 2 & 3 |
Answer» C. Options 1 & 3 | |
68. |
A fixed interval system |
A. | adds the same predetermined amount to inventory each time replenishment occurs |
B. | is suitable for joint replenishment items |
C. | is triggered at the reorder level |
D. | requires perpetual monitoring of inventory records |
Answer» C. is triggered at the reorder level | |
69. |
The outcomes of physical process modeling are ________ _________ showing tables and relationships with a database. |
A. | Process flow diagram |
B. | mServer model diagram |
C. | Entity relationship diagram |
D. | Control flow diagram |
Answer» C. Entity relationship diagram | |
70. |
The cycle time includes both_____________ as well as the _________time along with the idle time if any. |
A. | Balance delay. Service |
B. | Service time, productive |
C. | Productive, non-productive |
D. | Service time, non-productive |
Answer» D. Service time, non-productive | |
71. |
One factor impacting the fixed position input strategy is |
A. | Minimizing difficulties caused by material flow varying with each products |
B. | Requiring frequent contact close to one another |
C. | Balancing product flow one work station to the next |
D. | The movement of material to the limited storage areas around the site |
Answer» E. | |
72. |
Operations can be classified according to their volume and variety of production as well as the degree of variation & visibility . Which of the following operations would be classified as high volume , low variety ? |
A. | A front office bank |
B. | A family doctor |
C. | A carpenter |
D. | A fast food restaurant |
Answer» E. | |
73. |
Which of the following statements regarding a pull system is true ? |
A. | Large lots are pulled from upstream stations |
B. | Work is pulled to the downstream work stations before it is actually needed |
C. | Manufacturing cycle time is increased |
D. | Problems become more obvious |
Answer» E. | |
74. |
Which of the following would not normally be considered as a ‘costs of quality’ |
A. | Marketing costs |
B. | Prevention costs |
C. | Warranty costs |
D. | Rand D costs |
Answer» E. | |
75. |
The process through which inputs are converted into output is referred to as |
A. | The transformation process |
B. | Manufacturing |
C. | Materials management |
D. | Physical distribution |
Answer» B. Manufacturing | |
76. |
………………. Focused on the job and how to do it better |
A. | Scientific management |
B. | Bureaucratic management |
C. | Classical management |
D. | Administrative management |
Answer» B. Bureaucratic management | |
77. |
Which layout is used when a product is bulky, large, heavy or fragile? |
A. | Process layout |
B. | Product layout |
C. | Fixed position layout |
D. | Group technology layout |
Answer» D. Group technology layout | |
78. |
The two most basic inventory questions answered by the typical inventory model are |
A. | Timing and cost of orders |
B. | Quantity and cost of orders |
C. | Timing and quantity of orders |
D. | Order quantity and service level |
Answer» D. Order quantity and service level | |
79. |
Which of the following is true regarding forward scheduling? Forward scheduling is the scheduling of |
A. | The end items or finished products |
B. | Jobs as soon as the requirements are known |
C. | The start items or component parts |
D. | The final operations first beginning with the due date |
Answer» C. The start items or component parts | |
80. |
Scientific management contributed to the development of a more rational approach to management by developing which characteristics? |
A. | The planning and organization of work based on moral principles |
B. | Time and motion studies |
C. | Standardized pay |
D. | The encouragement of trade unions |
Answer» C. Standardized pay | |
81. |
________________ and _______________ are the two well-known methods of make or buy decisions. |
A. | Matching demand, level capacity |
B. | Forecast demand, matching demand |
C. | Dispatching, expediting |
D. | Estimating, routing |
Answer» B. Forecast demand, matching demand | |
82. |
The development and administration of the activities involved in transforming resources into goods and services is known as |
A. | Operations management |
B. | Manufacturing |
C. | The transformation process |
D. | Production |
Answer» B. Manufacturing | |
83. |
A represents activities and milestones by arcs and nodes |
A. | Conceptual data model |
B. | Physical data model |
C. | Project network model |
D. | Logical process model |
Answer» D. Logical process model | |
84. |
Time and motion study was introduced by |
A. | Hennery Fayol |
B. | F.W Taylor |
C. | Gilberth couple |
D. | Adam Smith |
Answer» C. Gilberth couple | |
85. |
Which of the following statements about the basic EOQ model is true |
A. | If ordering cost were to double , the EOQ would rise |
B. | If annual demand were to double , the EOQ would rise |
C. | If the carrying cost were to increase ,the EOQ would fall |
D. | All of the above statements are true |
Answer» B. If annual demand were to double , the EOQ would rise | |
86. |
Which of the following is the least likely decision to be made by operations managers ? |
A. | Selecting the locations and layout of a facility |
B. | Designing and improving the jobs of the workspace |
C. | How to use quality techniques to reduce waste |
D. | Deciding which market areas to manufacture products for |
Answer» E. | |
87. |
Which of the following is true for process layouts , hut false for production layouts ? |
A. | Low –in process inventories |
B. | Flexibility in equipment and labour arrangement |
C. | Low variety of products |
D. | High volume of output |
Answer» C. Low variety of products | |
88. |
Process technologies differ in their flexibility capabilities and economics and will therefore be appropriate for different parts of the volume – variety matrix. Flexible manufacturing systems are usually |
A. | Low variety , mid volume |
B. | Mid variety , high volume |
C. | Mid variety , mid volume |
D. | High variety , low volume |
Answer» D. High variety , low volume | |
89. |
All of the following statements about ABC analysis are true except |
A. | Inventory may be categorized by measures other than dollar volume |
B. | It categorizes on-hand inventory into three groups based on annual dollar volume |
C. | It is an application of the pare to principle |
D. | It states that all items require the same degree of control |
Answer» E. | |
90. |
Information technology companies follow ______________ strategy. |
A. | Chase demand strategy |
B. | Level production strategy |
C. | Stable work-force strategy |
D. | Differentiation strategy |
Answer» D. Differentiation strategy | |
91. |
Consider the below mentioned statements: 1. Quality circles are very efficient in executing low cost projects by using non-intrusive methods of improving productivity and quality throughout the organization. 2. In matching method, the production capacity is held constant at an optimum level. |
A. | 1-True, 2-true |
B. | 1-False, 2-True |
C. | 1-False, 2-False |
D. | 1-True, 2-False |
Answer» E. | |
92. |
Which of the following is not a function of purchasing management |
A. | Selecting the source |
B. | Placement of purchase order |
C. | Physical control of materials |
D. | None of these |
Answer» E. | |
93. |
— is a process of comparison with a superior performer anywhere in the world to improve quality. |
A. | Environmental scanning |
B. | Strategic decision making |
C. | Benchmarking |
D. | SWOT analysis |
Answer» D. SWOT analysis | |
94. |
The transportation model method that is used to evaluate location alternatives minimizes total |
A. | sources |
B. | destinations |
C. | capacity |
D. | shipping costs |
Answer» E. | |
95. |
Which approach is used to gain access to foreign markets and quickly promote an organization’s interest? |
A. | Joint venture |
B. | Technology transfer |
C. | Collaboration |
D. | Licensing |
Answer» B. Technology transfer | |
96. |
The fixed position layout would be most appropriate in which of the following cases |
A. | A fast food restaurant |
B. | A doctors office |
C. | A govt. restaurant |
D. | Constructing a Boeing277 |
Answer» E. | |
97. |
What are the two basic types of production systems? |
A. | Automated and manual |
B. | Intermittent and non-intermittent process |
C. | Normal and continuous process |
D. | Continuous process and batch |
Answer» C. Normal and continuous process | |
98. |
The major problem addressed |
A. | The movement of material to the storage areas around the site |
B. | Requiring frequent contact close to one another |
C. | The provision of low cost storage with low cost material handling |
D. | Minimizing difficulties caused by material flow varying with each product |
Answer» E. | |
99. |
Histograms are used for which of the following? 1. To record huge volumes of data about a process. 2. To indicate the extent of each category of problems in descending order of magnitude of the problem 3 To reveal if the pattern of distribution has a single peak, or many peaks. 4 To locate the points at which a problem exists. |
A. | Options 1 & 2 |
B. | Options 2 & 3 |
C. | Options 1 & 3 |
D. | Options 1 & 4 |
Answer» E. | |
100. |
Which of the following is not effectiveness criterion for scheduling? |
A. | Maximizing flow time |
B. | Maximizing completion time |
C. | Minimizing WIP inventory |
D. | Maximizing utilization |
Answer» B. Maximizing completion time | |