Which of the following is true regarding forward scheduling? Forward scheduling is the scheduling of |
A. | The end items or finished products |
B. | Jobs as soon as the requirements are known |
C. | The start items or component parts |
D. | The final operations first beginning with the due date |
Answer» C. The start items or component parts | |