1.

In a PERT/CPM network, computing the critical path requires

A. determining the total project duration
B. assigning the earliest finish time for an activity as the earliest start time for the next
C. that the latest finishing time for an activity not delay the overall project beyond initial expectation
D. a sophisticated and complex computer program
Answer» C. that the latest finishing time for an activity not delay the overall project beyond initial expectation


Discussion

No Comment Found