

MCQOPTIONS
Saved Bookmarks
This section includes 200 Mcqs, each offering curated multiple-choice questions to sharpen your Civil Engineering knowledge and support exam preparation. Choose a topic below to get started.
151. |
The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively$? |
A. | 80 and 90 |
B. | 90 and 80 |
C. | 85 and 75 |
D. | 75 and 83 |
Answer» E. | |
152. |
The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be$? |
A. | Rs. 8,800 |
B. | Rs. 7,600 |
C. | Rs. 6,400 |
D. | Rs. 5,000 |
Answer» D. Rs. 5,000 | |
153. |
For excavating utility trenches with precise control of depth, the excavation equipment used is$? |
A. | Hoe |
B. | Shovel |
C. | Dragline |
D. | None of the above |
Answer» B. Shovel | |
154. |
For completion of a project, the critical path of the network represents$? |
A. | Minimum time |
B. | Maximum time |
C. | Maximum cost |
D. | Minimum cost |
Answer» B. Maximum time | |
155. |
Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor$? |
A. | (i) and (iii) are correct |
B. | (i) and (iv) are correct |
C. | (ii) and (iii) are correct |
D. | (ii) and (iv) are correct |
Answer» C. (ii) and (iii) are correct | |
156. |
The main principle of an organization, is$? |
A. | Unity of command |
B. | Effective control at all levels |
C. | Delegation of authority |
D. | All the above |
Answer» E. | |
157. |
The difference between the time avail-to do a job and the time required to do the job, is known as$? |
A. | Event |
B. | Float |
C. | Duration |
D. | Constraint |
Answer» C. Duration | |
158. |
Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?? |
A. | Ice |
B. | Concrete |
C. | Loose sand |
D. | Earth |
Answer» E. | |
159. |
Final technical authority of a project lies with? |
A. | Assistant Engineer |
B. | Executive Engineer |
C. | Superintending Engineer |
D. | Chief Engineer |
Answer» E. | |
160. |
The basic action involved in sheep foot rolling is? |
A. | Kneading |
B. | Pressing |
C. | Tamping |
D. | Vibration |
Answer» B. Pressing | |
161. |
Which of the following does not represent an activity?? |
A. | Site located |
B. | Foundation is being dug |
C. | The office area is being cleaned |
D. | The invitations are being sent |
Answer» B. Foundation is being dug | |
162. |
A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be? |
A. | 3.7 years |
B. | 4.23 years |
C. | 5 years |
D. | 7.87 years |
Answer» C. 5 years | |
163. |
The independent float affects only? |
A. | Preceding activities |
B. | Succeeding activities |
C. | The particular activity involved |
D. | None of the above |
Answer» D. None of the above | |
164. |
The salient feature of functional organization is? |
A. | Strict adherence to specifications |
B. | Separation of planning and design part |
C. | Each individual maintains functional efficiency |
D. | All the above |
Answer» E. | |
165. |
In PERT analysis, the time estimates of activities and probability of their occurrence follow? |
A. | Normal distribution curve |
B. | Poisson's distribution curve |
C. | Beta distribution curve |
D. | None of the above |
Answer» D. None of the above | |
166. |
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?? |
A. | Yes, because of heavier overheads and handling cost |
B. | Yes, because of the very high order of quality control for the factory made components |
C. | No, because of repetitive manufacture of a number of elements |
D. | No, because of savings in site labour |
Answer» D. No, because of savings in site labour | |
167. |
A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he? |
A. | should invest in neither of the two projects |
B. | could invest in either of the two projects |
C. | should invest in project A |
D. | should invest in project B |
Answer» B. could invest in either of the two projects | |
168. |
Critical path lies along the activities having total float? |
A. | Positive |
B. | Negative |
C. | Zero |
D. | Same |
Answer» D. Same | |
169. |
CPM is? |
A. | Synthesising in concepts |
B. | Is built of activities oriented programme |
C. | Is based on time estimate |
D. | All the above |
Answer» E. | |
170. |
For the execution of a project, a contractor is? |
A. | A person |
B. | A firm |
C. | An agency |
D. | All the above |
Answer» E. | |
171. |
A Milestone chart? |
A. | Shows the interdependencies of various jobs |
B. | Depicts the delay of jobs, if any |
C. | Points outgoing ahead of schedule of jobs, if any |
D. | None of these |
Answer» E. | |
172. |
The main principle of an organization, is? |
A. | Unity of command |
B. | Effective control at all levels |
C. | Delegation of authority |
D. | All the above |
Answer» E. | |
173. |
A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will? |
A. | Reduce by 200 kg |
B. | Increase by 200 kg |
C. | Increase by 250 kg |
D. | Reduce by 250 kg |
Answer» B. Increase by 200 kg | |
174. |
A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be? |
A. | 15 minutes |
B. | 20.143 minutes |
C. | 21 minutes |
D. | 27 minutes |
Answer» D. 27 minutes | |
175. |
The difference between the time avail-to do a job and the time required to do the job, is known as? |
A. | Event |
B. | Float |
C. | Duration |
D. | Constraint |
Answer» C. Duration | |
176. |
The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be? |
A. | Rs. 8,800 |
B. | Rs. 7,600 |
C. | Rs. 6,400 |
D. | Rs. 5,000 |
Answer» D. Rs. 5,000 | |
177. |
The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively? |
A. | 80 and 90 |
B. | 90 and 80 |
C. | 85 and 75 |
D. | 75 and 83 |
Answer» E. | |
178. |
For completion of a project, the critical path of the network represents? |
A. | Minimum time |
B. | Maximum time |
C. | Maximum cost |
D. | Minimum cost |
Answer» B. Maximum time | |
179. |
For excavating utility trenches with precise control of depth, the excavation equipment used is? |
A. | Hoe |
B. | Shovel |
C. | Dragline |
D. | None of the above |
Answer» B. Shovel | |
180. |
Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor? |
A. | (i) and (iii) are correct |
B. | (i) and (iv) are correct |
C. | (ii) and (iii) are correct |
D. | (ii) and (iv) are correct |
Answer» C. (ii) and (iii) are correct | |
181. |
Free float for any activity is defined as the difference between |
A. | its earliest finish time and earliest start time for its successor activity |
B. | its latest start time and earliest start time |
C. | its latest finish time and earliest start time for its successor activity |
D. | its earliest finish time and latest start time for its successor activity |
Answer» B. its latest start time and earliest start time | |
182. |
Economic saving of time results by crashing |
A. | Cheapest critical activity |
B. | Cheapest noncritical activity |
C. | Costliest critical activity |
D. | Costliest noncritical activity |
Answer» B. Cheapest noncritical activity | |
183. |
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be |
A. | to + 3tm+ tp/3 |
B. | to + 4tm+ tp/4 |
C. | to + 4tm+ tp/5 |
D. | to + 4tm+ tp/6 |
Answer» E. | |
184. |
If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be |
A. | 50 % |
B. | Less than 50 % |
C. | More than 50 % |
D. | 100 % |
Answer» D. 100 % | |
185. |
If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is |
A. | 500 cum |
B. | 1000 cum |
C. | 1500 cum |
D. | 2000 cum |
Answer» B. 1000 cum | |
186. |
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is |
A. | 19 |
B. | 14 |
C. | 24 |
D. | None of these |
Answer» B. 14 | |
187. |
The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is |
A. | 3425 kg |
B. | 5515 kg |
C. | 4350 kg |
D. | 2975 kg |
Answer» C. 4350 kg | |
188. |
Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is |
A. | 1, 2, 4, 3, 5 |
B. | 1, 3, 2, 4, 5 |
C. | 1, 2, 3, 4, 5 |
D. | 1, 3, 4, 2, 5 |
Answer» D. 1, 3, 4, 2, 5 | |
189. |
During the construction period, price variation clause in contracts caters to |
A. | Increase in rates of only important materials |
B. | Variation in cost in materials element, labour element and petrol-oil-lubricant element |
C. | Variation in total cost of the project on an ad hoc basis |
D. | Rate of inflation |
Answer» C. Variation in total cost of the project on an ad hoc basis | |
190. |
PERT technique of network analysis is mainly useful for |
A. | Small projects |
B. | Large and complex projects |
C. | Research and development projects |
D. | Deterministic activities |
Answer» D. Deterministic activities | |
191. |
Military organization is known as |
A. | Line organization |
B. | Line and staff organization |
C. | Functional organization |
D. | None of these |
Answer» B. Line and staff organization | |
192. |
The most popular type of organization used for Civil Engineering Constructions, is |
A. | Line organization |
B. | Line and staff organization |
C. | Functional organization |
D. | Effective organization |
Answer» B. Line and staff organization | |
193. |
The main disadvantage of line organization, is |
A. | Rigid structure |
B. | Extraordinary delay in communications |
C. | Top level executions over work |
D. | All the above |
Answer» E. | |
194. |
A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be |
A. | 20 kg/tonne |
B. | 30 kg/tonne |
C. | 40 kg/tonne |
D. | 50 kg/tonne |
Answer» D. 50 kg/tonne | |
195. |
For which of the following materials, the output of power shovels for a fixed shovel size will be maximum |
A. | Moist loam |
B. | Good common earth |
C. | Well blasted rock |
D. | Wet sticky clay |
Answer» B. Good common earth | |
196. |
Latest start of an activity is always |
A. | greater than or equal to latest event time of preceding node |
B. | less than or equal to latest event time of preceding node |
C. | equal to latest event time of preceding node |
D. | less than latest event time of preceding node |
Answer» B. less than or equal to latest event time of preceding node | |
197. |
Which of the following is a weakness of bar chart? |
A. | Interdependencies of activities |
B. | Project progress |
C. | Uncertainties |
D. | All of the above |
Answer» E. | |
198. |
The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? |
A. | (i), (ii) and (iv) are correct |
B. | (ii), (iii) and (iv) are correct |
C. | (i), (iii) and (iv) are correct |
D. | (i), (ii) and (iii) are correct |
Answer» E. | |
199. |
Interfering float is the difference between |
A. | Total float and free float |
B. | Total float and independent float |
C. | Free float and independent float |
D. | None of the above |
Answer» B. Total float and independent float | |
200. |
The normal time required for the completion of project in the above problem is |
A. | 9 days |
B. | 13 days |
C. | 14 days |
D. | 19 days |
Answer» D. 19 days | |