MCQOPTIONS
Bookmark
Saved Bookmarks
→
Civil Engineering
→
Hydraulics And Fluid Mechanics in Civil Engineering
→
Critical path lies along the activities having tot..
1.
Critical path lies along the activities having total float?
A.
Positive
B.
Negative
C.
Zero
D.
Same
Answer» D. Same
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
Which one of the following is not an excavating and moving type of equipment?%!
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to%!
The area under the Beta distribution curve is divided into two equal parts by%!
Critical path method%!
Bar charts are suitable for%!
Updating may result in%!
In the given figure, the network of a project represents%!
Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is%!
In resources levelling%!
PERT is%!
Reply to Comment
×
Name
*
Email
*
Comment
*
Submit Reply