51. |
A spring of mean radius 40 mm contains 8 action coils of steel (N = 80000 N/mm2), 4 mm in diameter. The clearance between the coils being 1 mm when unloaded, the minimum compressive load to remove the clearance, is |
A. | 25 N |
B. | 30 N |
C. | 35 N |
D. | 40 N |
Answer» D. 40 N | |
52. |
If E, N, K and 1/m are modulus of elasticity, modulus of rigidity. Bulk modulus and Poisson ratio of the material, the following relationship holds good |
A. | <img src="/_files/images/civil-engineering/theory-of-structures/83-21-28-1.png"> |
B. | <img src="/_files/images/civil-engineering/theory-of-structures/83-21-28-2u.png"> |
C. | <img src="/_files/images/civil-engineering/theory-of-structures/83-21-28-3.png"> |
D. | all the above. |
Answer» E. | |
53. |
There are two hinged semicircular arches A, B and C of radii 5 m, 7.5 m and 10 m respectively and each carries a concentrated load W at their crowns. The horizontal thrust at their supports will be in the ratio of |
A. | 1 : 1 1/2 : 2 |
B. | 2 : 1 1/2 : 1 |
C. | 1 : 1 : 2 |
D. | none of these. |
Answer» D. none of these. | |
54. |
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be |
A. | started 5 days later |
B. | completed 5 days later |
C. | performed at slower rate in 15 days |
D. | all the above. |
Answer» E. | |
55. |
The object of technical planning, is |
A. | preparation of specifications |
B. | preparation of estimates |
C. | initiating the procurement action of resources |
D. | taking remedial action for likely bottleneck in the execution |
E. | all the above. |
Answer» F. | |
56. |
If TL is the latest allowable event occurrence time, total activity slack(s), is equal to |
A. | <i>LST-EST</i> |
B. | <i>LFT-EFT</i> |
C. | <i>TL-EFT</i> |
D. | all the above. |
Answer» E. | |
57. |
The Overall in-charge of an organisation at the site responsible for the execution of the works, is |
A. | Executive Engineer |
B. | Engineer |
C. | Junior Engineer |
D. | Sub overseer |
E. | Assistant Engineer. |
Answer» C. Junior Engineer | |
58. |
Modular co-ordination of construction means proper |
A. | planning |
B. | designing |
C. | execution |
D. | all the above. |
Answer» E. | |
59. |
A load of 1960 N is raised at the end of a steel wire. The minimum diameter of the wire so that stress in the wire does not exceed 100 N/mm2 is : |
A. | 4.0 mm |
B. | 4.5 mm |
C. | 5.0 mm |
D. | 5.5 mm |
E. | 6.0 mm |
Answer» D. 5.5 mm | |
60. |
The radius of gyration of a section of area A and least moment of inertia I about the centroidal axis, is |
A. | <img src="/_files/images/civil-engineering/theory-of-structures/86-21-62-1.png"> |
B. | <img src="/_files/images/civil-engineering/theory-of-structures/86-21-62-2.png"> |
C. | <img src="/_files/images/civil-engineering/theory-of-structures/86-21-62-3.png"> |
D. | <img src="/_files/images/civil-engineering/theory-of-structures/86-21-62-4.png"> |
Answer» D. <img src="/_files/images/civil-engineering/theory-of-structures/86-21-62-4.png"> | |
61. |
In plastic analysis, the shape factor for rectangular section, is |
A. | 1.4 |
B. | 1.5 |
C. | 1.6 |
D. | 1.7 |
Answer» C. 1.6 | |
62. |
CPM is |
A. | synthesising in concepts |
B. | is built of activities oriented programme |
C. | is based on time estimate |
D. | is used for repetitive works |
E. | all the above. |
Answer» F. | |
63. |
Principal planes are subjected to |
A. | normal stresses only |
B. | tangential stresses only |
C. | normal stresses as well as tangential stresses |
D. | none of these. |
Answer» B. tangential stresses only | |
64. |
In plastic analysis, the shape factor for a circular section, is |
A. | 1.5 |
B. | 1.6 |
C. | 1.7 |
D. | 1.75 |
Answer» D. 1.75 | |
65. |
A critical ratio scheduling |
A. | establishes the relative priorities among various activities on a common basis |
B. | determines the status of each activity |
C. | adjusts automatically changes in activity progress |
D. | is a dynamic system |
E. | none of these. |
Answer» F. | |
66. |
The first method invented for planning projects, was |
A. | Bar chart method |
B. | Milestone chart |
C. | Critical path method (CPM) |
D. | Programme Evaluation and Review Technique (PERT) |
Answer» B. Milestone chart | |
67. |
An Executive Engineer may have powers upto |
A. | Rs. 25,000 |
B. | Rs. 50,000 |
C. | Rs. 100,000 |
D. | Rs. 200,000 |
E. | Rs. 500,000 |
Answer» B. Rs. 50,000 | |
68. |
"An Electromagnetic wave falls on to a boundary between two loss less homogeneous media with different refractive indices, a part of the wave is reflected back to the incident medium and the rest is transmitted on to the second media". This phenomenon is known as : |
A. | Fresnel reflection |
B. | Fresnel refraction |
C. | Snell's law |
D. | None of these |
Answer» B. Fresnel refraction | |
69. |
Remote sensing techniques makes use of the properties of-----emitted, reflected or diffracted by the sensed objects: |
A. | electric waves |
B. | soundwaves |
C. | electromagnetic waves |
D. | wind waves |
Answer» D. wind waves | |
70. |
The value of energy quantum for radiation of any frequency is proportional to : |
A. | the frequency |
B. | the reciprocal of the energy |
C. | the square of the frequency |
D. | the square root of the frequency |
Answer» B. the reciprocal of the energy | |
71. |
The phase difference of the waves 1 and 2 at A in the given figure is : |
A. | /4 |
B. | /2 |
C. | |
D. | 3 /2 |
Answer» C. | |
72. |
The basic requirement of any sensor system, is : |
A. | radiometric resolution |
B. | spatial resolution |
C. | spectral resolution |
D. | temporal resolution |
E. | All of these |
Answer» F. | |
73. |
Henry Gantt developed Bar charts for planning and scheduling of projects in |
A. | 1880 |
B. | 1900 |
C. | 1920 |
D. | 1940 |
E. | 1950 |
Answer» C. 1920 | |
74. |
Leaf reflactance depends primarily on : |
A. | the pigments |
B. | internal cell structure |
C. | equivalent water content |
D. | All of these |
Answer» E. | |
75. |
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as |
A. | duration |
B. | total flat |
C. | free float |
D. | interfering float. |
Answer» D. interfering float. | |
76. |
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as |
A. | event |
B. | free float |
C. | dummy |
D. | constant |
Answer» D. constant | |
77. |
The reflection of solar energy is characterised by the water content in the leaf, in the reflective optical infrared: |
A. | visible (0.4 - 0.7 m) region |
B. | near-IR (0.7 - 1.3 m) region |
C. | short wave-IR (1.3 - 2.7 m) region |
D. | None of these |
Answer» D. None of these | |
78. |
A reduction of nitrogen nutrient in plants : |
A. | affects leaf colour |
B. | reduces pigment concentration |
C. | increase the visible reflectivity |
D. | All of these |
Answer» E. | |
79. |
Which one of the following parameters is considered to determine the reflectance of a vegetation canopy |
A. | Solar zenith angle |
B. | Azimuth angle |
C. | Look angle |
D. | Number and arrangement of leaves |
E. | All of these |
Answer» F. | |
80. |
The most widely used antenna in GPS is |
A. | Parabolid antenna |
B. | Microstrip antenna |
C. | Horn antenna |
D. | Slotted antenna |
Answer» C. Horn antenna | |
81. |
Which one of the following residual biases involves the GPS accuracy ? |
A. | Satellite dependent baises due to uncertainty in the orbital parameters of the satellite. |
B. | Receiver-depandent biases due to clock stability with line |
C. | Signal propagation baises due to the sphere and troposphere propogation. |
D. | All the above |
Answer» E. | |
82. |
Which one of the following statements regarding remote sensing is correct. |
A. | The interaction of the electromagnetic radiation with the target |
B. | The emission of electromagnetic radiation from the target |
C. | both (a) and (b) |
D. | Neither (a) nor (b) |
Answer» D. Neither (a) nor (b) | |
83. |
Pick up the correct definition from the following with response to GIS. |
A. | Common boundry between two areas of a locality is known as adjacency. |
B. | The area features which are wholly contained within another area feature, is known so containment. |
C. | The geometric property which describes the linkage between line features is defined as connectivity. |
D. | All of these. |
Answer» E. | |
84. |
Which one the following is a correct statement? |
A. | The vertical section of the soil extending into the parent material, is called profile |
B. | The layers of the soil parallel to the earth surface, are called horizons. |
C. | The transitional layer between two adjoining horizons, is called boundary. |
D. | All of these |
Answer» E. | |
85. |
The coherence length over which there is a strong relationship between amplitudes is; |
A. | directly proportional to the bandwidth |
B. | inversely proportional to the bandwidth |
C. | the square of the bandwidth |
D. | none of these |
Answer» C. the square of the bandwidth | |
86. |
Which one of the following helps to identify the objects on the earth surface ? |
A. | atmospheric window |
B. | signature |
C. | radiometric error |
D. | None of these |
Answer» C. radiometric error | |
87. |
Rayleigh's criteria for a rough surface is: (where letters carry their usual meanings). |
A. | h > / cos |
B. | h = /8 cos |
C. | h > /8 cos |
D. | h < /8 cos |
Answer» D. h < /8 cos | |
88. |
The most popular type of organisation used for Civil Engineering Constructions, is |
A. | line organisation |
B. | line and staff organisation |
C. | functional organisation |
D. | effective organisation. |
Answer» B. line and staff organisation | |
89. |
The main principle of an organisation, is |
A. | unity of command |
B. | cohegency |
C. | effective control at all levels |
D. | delegation of authority |
E. | all the above. |
Answer» F. | |
90. |
The estimated time required to perform an activity, is known as |
A. | event |
B. | dummy |
C. | duration |
D. | float. |
Answer» D. float. | |
91. |
A CPM family includes |
A. | CPA (Critical Path Analysis) |
B. | CPP (Critical Path Plotted) |
C. | MCE (Minimum Cost Expenditure) |
D. | CPS (Critical Path Scheduling) |
E. | All the above. |
Answer» F. | |
92. |
Construction team means |
A. | an engineer |
B. | an architect |
C. | an owner |
D. | a contractor |
E. | all the above. |
Answer» F. | |
93. |
A construction schedule is prepared after collecting |
A. | number of operations |
B. | output of labour |
C. | output of machinery |
D. | quantity of various items |
E. | all the above. |
Answer» F. | |
94. |
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is |
A. | <img src="/_files/images/civil-engineering/construction-management/74-19-74-1.png"> |
B. | <img src="/_files/images/civil-engineering/construction-management/74-19-74-2.png"> |
C. | <img src="/_files/images/civil-engineering/construction-management/74-19-74-3.png"> |
D. | <img src="/_files/images/civil-engineering/construction-management/74-19-74-4.png"> |
Answer» D. <img src="/_files/images/civil-engineering/construction-management/74-19-74-4.png"> | |
95. |
The ratio of maximum shear stress to average shear stress of a circular beam, is |
A. | <img src="/_files/images/civil-engineering/theory-of-structures/87-21-76-1.png"> |
B. | <img src="/_files/images/civil-engineering/theory-of-structures/87-21-76-2.png"> |
C. | <img src="/_files/images/civil-engineering/theory-of-structures/87-21-76-3.png"> |
D. | <img src="/_files/images/civil-engineering/theory-of-structures/87-21-76-4.png"> |
Answer» E. | |
96. |
Coal ash (or cinder) is used in initial stages of a new construction of railway for |
A. | wooden sleepers |
B. | steel sleepers |
C. | cast iron sleepers |
D. | none of these. |
Answer» B. steel sleepers | |
97. |
Works costing less than Rs. 20,000 are treated as |
A. | projects |
B. | major projects |
C. | minor projects |
D. | all the above. |
Answer» D. all the above. | |
98. |
A rolled steel joist is simply supported at its ends and carries a uniformly distributed load which causes a maximum deflection of 10 mm and slope at the ends of 0.002 radian. The length of the joist will be, |
A. | 10 m |
B. | 12 m |
C. | 14 m |
D. | 16 m |
E. | 18 m |
Answer» E. 18 m | |
99. |
A steel rod 1 metre long having square cross section is pulled under a tensile load of 8 tonnes. The extension in the rod was 1 mm only. If Esteel = 2 x 106 kg/cm2, the side of the rod, is |
A. | 1 cm |
B. | 1.5 cm |
C. | 2 cm |
D. | 2.5 cm |
Answer» D. 2.5 cm | |
100. |
The maximum deflection due to a uniformly distributed load w/unit length over entire span of a cantilever of length l and of flexural rigidly EI, is |
A. | <img src="/_files/images/civil-engineering/theory-of-structures/88-21-84-1.png"> |
B. | <img src="/_files/images/civil-engineering/theory-of-structures/88-21-84-2.png"> |
C. | <img src="/_files/images/civil-engineering/theory-of-structures/88-21-84-3.png"> |
D. | <img src="/_files/images/civil-engineering/theory-of-structures/88-21-84-4.png"> |
Answer» D. <img src="/_files/images/civil-engineering/theory-of-structures/88-21-84-4.png"> | |