MCQOPTIONS
Saved Bookmarks
1. |
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be |
A. | started 5 days later |
B. | completed 5 days later |
C. | performed at slower rate in 15 days |
D. | all the above. |
Answer» E. | |