

MCQOPTIONS
Saved Bookmarks
1. |
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is |
A. | <img src="/_files/images/civil-engineering/construction-management/74-19-74-1.png"> |
B. | <img src="/_files/images/civil-engineering/construction-management/74-19-74-2.png"> |
C. | <img src="/_files/images/civil-engineering/construction-management/74-19-74-3.png"> |
D. | <img src="/_files/images/civil-engineering/construction-management/74-19-74-4.png"> |
Answer» D. <img src="/_files/images/civil-engineering/construction-management/74-19-74-4.png"> | |