1.

Your company has a policy of having every software project reviewed and approved by the Architecture Review Board prior to the construction  phase of a project. you are currently in the process of activity sequencing. This is a example of what?

A. Gatekeeping
B. Milestone
C. New scope for the project
D. Project integration
Answer» C. New scope for the project