| 1. |
Which of the following is not true about bottom-up estimating? |
| A. | The WBS must be accurate and complete before this process can be used. |
| B. | Since the cost is largely independent of the desired accuracy it is the methodology of choice. |
| C. | Its accuracy increases if the activities are smaller. |
| D. | It is not a useful methodology in the early project planning phase. |
| Answer» C. Its accuracy increases if the activities are smaller. | |