| 1. |
Why are CPM, GERT, and PERT not considered sufficient to create a project schedule? |
| A. | All three are tools and techniques of schedule development, not the actual schedule |
| B. | As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations |
| C. | They are sufficient. Each calculates early and late start and finish dates for each activity |
| D. | They are Monte Carlo techniques used to provide what-if analysis for adverse external factors on a project |
| Answer» C. They are sufficient. Each calculates early and late start and finish dates for each activity | |