1.

X, Y and Z can do a piece of work in 30 days, 45 days and 90 days respectively. In how many days can the work be completed if X is assisted by Y and Z together, on every second day?

A. 10 days
B. 20 days
C. 15 days
D. 30 days
Answer» C. 15 days