X can do \(\frac{1}{2}\) of a work in 8 days. Y can do 30% of the same work in 50 days and Z can do \(\frac{1}{4}\) of the same work in 20 days. Who will complete the work last?

A. Y
B. Z
C. X
D. X and Y
Answer» B. Z