X alone can complete a work in 6 days and Y alone can complete the same work in 30 days. If X and Y work together, then in how many days work will be completed? |
| A. | 5 |
| B. | 4 |
| C. | 6 |
| D. | 4.5 |
| Answer» B. 4 | |