Working together, A and B can complete a work in 12 days. They work together for 9 days after which B leaves. If A finishes the remaining work in 5 days, then the number of days that B alone would take to complete the work is: |
| A. | 12 |
| B. | 15 |
| C. | 24 |
| D. | 30 |