Working 5 hours a day, A can complete a piece of work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they both can complete the work in: |
| A. | 4 days |
| B. | 5.4 days |
| C. | 4.5 days |
| D. | 3 days |
| Answer» E. | |