Worker A takes 8 days to do a job. Worker B takes 10 days to do the same job. How long should it take for both A and B, working together, to do the same job?

A. \(4\frac{4}{9}\) days
B. \(4\frac{1}{9}\) days
C. \(4\frac{5}{9}\) days
D. \(4\frac{3}{9}\) days
Answer» B. \(4\frac{1}{9}\) days