Workability of concrete can be measured using slump, compaction factor and Vee-bee time. Consider the following statements for workability of concrete:(i) As the slump increases, the Vee-bee time increases.(ii) As the slump increases, the compaction factor increases.Which of the following is TRUE?

A. Both (i) and (ii) are True
B. Both (i) and (ii) are False
C. (i) is True and (ii) is False
D. (i) is False and (ii) is True
Answer» E.