Within what temperature range should the tack coat be applied?
A.
30 – 40°C
B.
20 – 50°C
C.
34 – 44°C
D.
24 – 54°C
Answer» E.
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
Boulders are preferred in the construction of the base course because of their strength.
Which of the below doesn’t represent the purpose of providing a base course in the rigid pavement?
Acrylic sealer is preferred to fast dry sealers.
What type of surface course is provided in a semi-rigid pavement?
What is the thickness of the binder course that is provided in the pavement?
Within what temperature range should the tack coat be applied?
Frost protection layer is provided in between which layers?
It is important to ensure that the subgrade is not ______ at any time.
Which of the below is not a purpose of providing a prime coat?
Flexible pavement consists of ______ course after subgrade course.
Reply to Comment
×
Name
*
Email
*
Comment
*
Submit Reply