1.

NPV method is used to estimate the costs in the life cycle cost analysis.

A. True
B. False
Answer» C.
2.

What is the main aim of the pavement design process?

A. Weathering
B. Compaction
C. Thickness
D. Strength
Answer» D. Strength
3.

What is the first step in the construction process of a new pavement?

A. Site investigation
B. Traffic data
C. Determining cross-section
D. Evaluate drainage
Answer» C. Determining cross-section
4.

Which of the below is not a user cost considered in the life cycle cost analysis?

A. Sunk cost
B. Delay costs
C. Vehicle operating cost
D. Crash costs
Answer» B. Delay costs
5.

A parallel road is an example of new pavement construction.

A. True
B. False
Answer» B. False
6.

What step comes after the initial strategy is decided in the life cycle cost analysis method?

A. Estimating costs
B. Analyzing results
C. Evaluating strategies
D. Comparing alternatives
Answer» B. Analyzing results
7.

Which of the below is not a pavement design category?

A. New pavement
B. Pavement reconstruction
C. Pavement rehabilitation
D. Pavement demolition
Answer» E.
8.

Which method is used to determine the most cost-effective design and construction procedure?

A. Cost-benefit analysis
B. Deductive economic analysis
C. Life cycle cost analysis
D. Inductive economic analysis
Answer» D. Inductive economic analysis
9.

What is the factor that ensures a good pavement design process?

A. Communication
B. Location
C. Fund
D. Climate
Answer» B. Location
10.

______ design needs to be conducted during the early phase of the project.

A. Primary
B. Preliminary
C. Trial
D. Initial
Answer» C. Trial