| 1. |
With P starting the work, working on alternate days, P and Q can finish a work in 17 days. If Q works on the first day and Q and P work alternately, the work is finished in 53/3 days. How many days will each take individually to execute the work? |
| A. | P = 35 days; Q = 35 days |
| B. | P = 35/3 days; Q = 35 days |
| C. | P = 12 days; Q = 35 days |
| D. | P = 35 days; Q = 35/3 days |
| Answer» C. P = 12 days; Q = 35 days | |