Which of the following relations are correct for determining different components of a bid price?1. Bid price = Direct cost + Indirect cost + Mark up amount2. Direct cost = Project overheads + Common plant and equipment cost + Common work men cost3. Mark up amount = Profit + Contingency + Allowances for risks + General overheads |
| A. | 1, 2 and 3 |
| B. | 1 and 2 only |
| C. | 1 and 3 only |
| D. | 2 and 3 only |
| Answer» D. 2 and 3 only | |