Which of the following pairs are correctly matched ?Feature Type of Budget1. Allows no proper : Incremental budgetincentive for managers todevelop innovative ideas2. Increases staff motivation : Zero-based budget3. The R u0026 D department : Zero-based budgetis threatened whereasproduction departmentbenefits4. The impact of change : Incremental budgetcan be seen quicklySelect the correct answer using the code given below-- |
| A. | 1, 2 and 3 only |
| B. | 2, 3 and 4 only |
| C. | 1 and 4 only |
| D. | 1, 2, 3 and 4 |
| Answer» B. 2, 3 and 4 only | |